Sunday, December 18, 2022

A December to Remember

Even though we are only half way through the month, we have had enough excitement & challenges for a few months!  We long for the sunshine of southern Arizona in the desert right about now.  This building a house business as your own general contractor is a serious challenge.  We think and hope this will be the last time we attempt this.  We are still very excited to finish this project and move in and finally use the place that we have put so much of ourselves into; no regrets there.  We are beat down and exhausted some days and just want the building adventure to be over!  We have had much good progress this month and expect more before Christmas and even more right after New Year Day.  We can see the finish line coming over the horizon finally.  It is still a ways off, but much closer than it has been.

This is what we should be doing, but thanks to our neighbor Cory Nielsen for capturing this awesome local Swan Valley image.  As you can imagine from this picture, we have had our fair share of snowfall and cold temperatures here, and only half way through December 😮

Rather, what we have been busy doing in the first part of December is chasing leaks in our DWV  (Drain-Waste-Vent) plumbing system.  The shot below is the kitchen drain-vent.  We installed it initially, but the inspector wanted us to install the drain pipe in the walls not through the floor where it was easily accessible, protected from the exterior cold and didn't leak.  We hired a local professional  plumbing company to do the tricky install in the wall.  The inspector didn't pass their first attempt either, they didn't like the pipe sizing.  So the plumber reinstalled the system with the larger drain pipe, 2".  Passed inspection, but now it leaks under the pressure test.  Plumber came back three more times on that install before it was finally complete, passed inspection and didn't leak.  Including our effort that was five tries on this area of our drain system.  We had to rip out the plastic and insulation so the plumber could get back in there and do the last rework.  You may start to see why we may remember this December for a few more days...

Below is one of the leaks that we found in the DWV system, this one is part of the kitchen area.  When we pressurized the system, we knew there was a leak or leaks somewhere because the system would lose pressure in an hour or less.  We found one leak, fixed that, then realized there was another.  Finally we just tested every DWV joint; I guess there are near 100 joints, some really hard to get at for test.  The test is to pressurize the system then spray soapy water on the joint.  If you see bubbles growing that is a leak.  We are proud to report that we did not find a single leak in any of the joints that we installed and glued, and we installed 90% of the system.  It was just the professionally installed fittings that gave us a fit!

Another leak, also part of the kitchen.  Gotta fix that!
Below is a shot of a clean out, which is required here on all drains.  We didn't know that, so didn't initially install them.  The plumber we hired did this for us.  They installed about 8 of these fittings of which 3 leaked and had to be replaced.
Same clean out, you can see the pressurization set up we used in the background..  The pressurization input was at this drain for the utility sink in the guest bath/laundry room.

Plumbers Eric & Brendon go at the last and successful refit of the kitchen area.

All put back together.  Gari still has on her respirator from replacing the insulation.  There, wasn't that easy?  We did that with three pictures haHahA (crazy person laugh)!

Not so fast, we still had not leaked checked all the fitting joints in the attic on the vent system, so we went up there with our soapy water spray bottle on a Friday morning 12/9.  Coincidentally we had a pretty good snow storm roll through on the Thursday night before.  Then within a few minutes of being up in the attic I noticed this...  See the snow accumulating at the roof ridge?  NOT Good!

The storm had 50 mph wind gusts and lots of fine as powder snow flakes.  We believe this is what forced the snow through any tiniest of cracks, and we believe some still exist in the roof ridge vent system.... obviously.  Once the snow passed the ridge vent and was inside the building, it pretty much fell straight down from the roof ridge.  The vertical member in the picture below is the roof truss kingpost that goes straight up to the roof ridge.  You can see the snow on the diagonal truss brace and I scooped a handful of snow off of the face of the fiberglass insulation. The insulation is a bright white so it is hard to see the snow on it, but it is there.
The snow fell on everything right below the ridge, the wires, the electrical boxes the pipes and ducts.
Gari looks up at the ridge vent in over the garage.  Snow entered at every single roof panel bay in the garage and in more than half of the roof panel bays over the house area.  A real gut punch when we discovered it!
It is difficult to see up in the ridge what is going on in each roof panel bay because of the location (10 ft up) and because of the small clearance of about 1 inch.  We stuffed the camera up in that gap and got this photo below.  Obviously light is coming in abundantly at the joint formed at the interface of the roof panel standing seam and the Z-metal installed to fill the gap.  That joint should have sufficient caulk at installation so as no gap remains and will block any and all wind driven snow or moisture.  Doesn't look sealed very well to us.   We are in discussion with the installing contractor.
Zooming out, the shot below shows a section of roof ridge above the house.  Now that the attic is closed in with insulation, it is much darker up there and we could see this light much better, which we had missed before when this area was all open and much lighter up there.  Several of the bays obviously have light entering, suggesting gaps may exist. This is where the snow entered at the joint of the standing seam to Z-metal at many of the roof panel bays.
We developed a plan.  The first thing we could implement was to install the left over vapor barrier on either side of the truss king posts.  The plastic extends about 4 foot on either side of the kingpost or roof ridge.  We made a swale in the plastic on each side of the kingpost so it would capture and snow or other moisture that may enter the attic in the future and keep it out of the insulation.  The second part of our plan is to install additional horse hair or hog hair air filter media in each roof panel bay to further fill any existing gaps there.  The ridge vents are constructed with this same filter media, we are just going to stuff more in there.  The last phase is to remove a few of the roof ridge caps, inspect the standing seam to Z-metal joints for proper caulk and butyl tape on the bottom flange of the Z.  If more than one joint is inadequate, we have asked the installer to remove all ridge caps and correct all joints under workmanship warranty.  If the sample of 2 or 3 ridge caps removed all looks good we will pay for the sample inspection.  We will see how that proposal works...

Friday was spent removing snow with a 5 gallon bucket.  We removed as much as we could on Friday.  We were so upset we gave out early that Friday.

After a good rest overnight we were re-energized and went back at it on Saturday.  Upon entering the house we noticed this in one of our large picture windows.  It looked like a .22 round.  Upon further investigation we think it was from a pellet air gun.  Right after discovering the attic snow the day before we were not prepared for this.  It was hard to get over the idea that someone was shooting directly at our house.  Either intentionally or unintentionally didn't seem to make much difference.  We called the sheriff and a deputy came out, performed an investigation and made a report.  So now we wait and we watch.

We have figured out that we can just replace the glass... for $1200.  We have filled the hole with silicone caulk until we can make the repair.

Now back to good progress.  The drywall arrived one snowy overcast day last week.  Jose operates the squirt boom crane on the delivery truck with his wireless remote control panel.  He was good with the crane.

He brought the boom and payload right to the front door and they transferred the sheetrock over to a dolly at the door.
They had one load get away from them when transferring the sheets.  It knocked the cart off of the ramp at the door and slammed against the door.  After inspecting things it appears that we avoided any damage.  That stuff is heavy!
The guys loaded the appropriate number of sheetrock bundles into each room to make it easy for the installers.
A couple days later the installers showed up.  Luis, the team lead, gives me the thumbs up from his drywall stilts as I capture some documentation.  The guy on the bucket actually walked across the floor without getting off of the bucket.  Now we have seen these high up workers walk on step ladders and now buckets!  Luis was a great guy and the crew was very nice and they did a neat job hanging everything.  One guy worked in a Santa Claus hat and fuzzy white collar!  They completed the hanging task in a day and a half.  We expect them to return this week to start the tape, mud & texture.
Luis and helper on our scaffold hanging the heavy stuff on the garage ceiling.
I am bigger than Luis, but I don't believe that I could do what he does!  He has some serious power and technique in his smaller frame.
All hung out.  Really starting to look like a house now.  Inconvenient though, we can no longer walk through the walls.  Sitting room looking east toward Mt Baldy and the lake.  You can just see the gas log stub out in the corner coming out of the floor.
Looking at the kitchen sink area.  You can see the drain pipe below the window.  The wires protruding from the walls will be over cabinet accent lights and under cabinet work lights.
Looking at the oven and refrigerator wall.  You can see the stove vent hood duct up high frame center, and the refrigerator ice maker connection at frame left low.
Guest bedroom looking back out the door and at the closet.
Guest bathroom/laundry room.  You can just see the dryer vent at frame left low.  The toilet will be tucked in the nook behind the shower/tub, past that will be a little closet nook to hang clothes as they come out of the dryer.
Guest bath looking back out the door; l to r: lav, utility sink; washer is just out of frame to the right, but you can just see the washer electrical outlet at frame right.
Looking into the pantry.  First room in the hall next to kitchen.  You can see the crawlspace access opening in the floor.
Master bedroom looking from just inside the master bath door.
Master Bath.  One person sauna planned for the right corner.  Toilet will be tucked behind the shower wall to the left.  Lavs are just out of frame to the right - across from the shower.
Entry hall from garage.  Thermostat wire at left, followed by guest bed, then guest bath.  On the right is the utility closet (water heater), then the coat closet, and at the end of the hall is the door out into the garage.  The pantry is just before the thermostat wire at the left just out of frame.  The master bedroom door is just out of frame at right.

Garage drywall.  The installers only hung the ceiling and the firewall in the garage.  We will install OSB sheathing to the other 3 walls.  We already have a few sheets up on the south wall from the framing leftovers.  You can see the attic access hatch in the ceiling.  This is the only attic access point.   The outlet box by the attic access is for a ceiling fan.

A view out our front yard looking east toward Mt. Baldy, Sheep Mt, and the Palisades Reservoir.  It's cold here.  I should add that our kitchen cabinets arrived a week ago, so as soon as the drywall is finished and we can get the paint applied we will have the kitchen and bathroom cabinets installed.  Final electrical devices and fixtures as well as final plumbing fixtures can then also be installed.  That should keep us busy for a week or more.  Still remaining is the trim, baseboard, doors and windows.  We have the interior doors on order.  Finally there is the matter of the flooring.  We are planing to install plank vinyl ourselves.  That should be an adventure in and of itself.  We also have a plan for a little tile work; at the front door entry and under the gas log in the corner of the sitting room. 

Another gorgeous shot from neighbor Corey.  Wishing a Merry Christmas to all and all the best in the New Year.  We can all be saved through Jesus Christ!

Sunday, December 4, 2022

Snow Blind

November is in the books and we now make our way into December for the final chapter of 2022.  It seems like we have had a lot of snow already this season, but apparently it is less than last year we are told.  No complaints about that.  The temperatures have been a bit below the norm for this early in the season.  We are already experiencing single digit and even negative overnight temperatures.  So far the water continues to run into the shop.  Hooray!

Our house and shop on the right as we make our way down our snow covered road after a trip in town to Idaho Falls for supplies and appointments.  I think all the rest of the outside shots will be snow scenes for the next three months or so.

From our house window while we took a union break.  I call that one horse Idaho, for his marking.  We understand these are bucking broncs.  They are hearty specimens for sure.
The insulation contractor came and installed R-21 faced fiberglass batts in the walls and 6 mil plastic vapor barrier on the ceilings.  This is the garage and the last area of the day and job.
We came behind the insulators, policed up the rushed job and improved the fit in each stud bay then covered the exterior walls with the same 6 mil plastic vapor barrier.  This is a view of the eat in kitchen.
Below is a view of the sitting room.  We got lucky and have a drywall contractor scheduled for late this week.  WE will see what happens with that.  It is supposed to be a two day hang job and a week or two finishing and texturing.  If all that happens we will start painting immediately.... the kitchen and bathroom cabinets are also supposed to arrive late this week.  Should be an interesting upcoming week.
Captured a shot of the HVAC air handler installed on hangers in the crawlspace.  You can see the EPS or Expanded Polystyrene foam board in the foreground at frame left and in the background at frame right. Our plan is to install two courses on the ground of the crawlspace and then cover with the yellow 10 mil plastic vapor barrier.  We have all of the exterior walls completed.  We are waiting for the plumbing to be completed before we lay the foam and vapor barrier on the ground.  Our plumbing contractor has a call back to correct a joint leak in the kitchen drain they installed.
Dropping down into the valley of the East Fork of the Snake River at Swan Valley.


Sunday, November 13, 2022

Mid November

The beginning of winter has arrived in Swan Valley.  Nevertheless, we continue to move forward with house construction.  Below is about the third snow storm, this one brought about 6 inches of snow and drifts of 2 feet or more.

It seems appropriate that we are now pursuing insulating the house since we finally passed our rough electrical and plumbing inspections.  A major victory for us.  We established a contract with an insulation contractor where they would supply R21 kraft faced fiberglass batts for the house and garage ceiling that we would install.  The,, the contractor will install all the R21 insulation batts in the walls of the house and garage, and install 6 mil plastic vapor barrier on the ceilings in the house and garage as well.  Then we will come in again and install the 6 mil plastic vapor barrier on the walls in house and garage.  Once we figure out how to get the drywall installed, then the insulation contractor will come back and blow in an additional R30 or about another 17 inches of insulation in the attic over the house and garage to give us about R51 in the ceilings. 
We started in the big room...there's Gari all suited up in her PPE and up on the ladder.  You can see the snow out the window; it will be good to have the place insulated.  And now that we are about finished with handling insulation batts ourselves, it is very good to get out of those respirators.
The kitchen and great-room ceilings are now insulated below.  You can see the little electric space heater we are using to put a little warmth inside the house.
We used the scaffolding in the garage with the 12 foot ceilings.  Gari surveys the few gaps remaining.
We boxed in a couple ducts that came into the living space out of necessity for drywall installation.  You can just see the range hood duct and box at frame right up high.
Steve is busy cutting in the electric service panel below.
All finished...except for the service entrance cable.  We will install that in the spring when we can pull the cable from the shop and switch the shop over to a 100 Amp service.
We contracted with a local Idaho Falls company to install a propane forced air furnace in the crawlspace with a 3 ton air conditioner.  Below is a shot of the compressor going onto its' pad.  We wanted a Trane system, but apparently because of supply chain issues with Trane it was a 6 month wait for a system and repair parts seemed uncertain.  Therefore, we went with Japanese Diakin system.  It seems very well built with good quality.  We will see how it performs test by Idaho weather.

Below, Jacob the HVAC installer finishes up the AC system with a refrigerant charge, whilst the roofers repair a defect we found in the ridge cap.

Gari prepares the pressure test for the plumbing supply system below.
Steve installs the LED flood light over the garage door.

Just about finished..

Until next post, we will be working to get the inside of the house looking more complete like the outside.


 


 




Monday, October 3, 2022

September Accomplishments

We continue to push the rock up the hill every weekday and Saturdays.  As a result things are getting done.

Our neighbor Mrs #22.  A curious and friendly gal she is.

OK, we did take an afternoon off.  The Hansen Guest Ranch put on an Oktoberfest celebration in cooperation with the Chamber of Commerce in Swan Valley.  The food was excellent, Bratwurst & Sauerkraut, Schnitzel, Spätzle, soft pretzels, and German Chocolate Cake. They had Sam Adams Autumn Ale on tap and even had live music.  This two little gals could really sing.  They sang a couple dozen songs from God Bless America to Sweet Home Alabama, but they customized it to Sweet Home Swan Valley!  They were outstanding entertainers!
We even met up with Casey and his new bride Abby from North Carolina, at the end of the event.  They were touring the USA for their Honeymoon.  They didn't have set plans, just woke up each day and decided what they wanted to do.  We think they would make good RVers!

We worked on spreading all the gravel that Troy hauled in.  Gari had the hard ground work on this deal.

We finished raking and smoothing and compacting just in time for Tom & Cathy's arrival.

Below is the Irwin Rd driveway.  We started lining the edge of the driveway with river rock we plucked out of the yard area.  We stopped because we think we are going to have to push snow off the driveway and the edge rocks will be in the way of that.


Looking north out the Chapel Road driveway.
Looking east out the Irwin Rd driveway.  We straightened the edges of this driveway; better than it was before anyway.

 At the end of the Irwin Rd driveway, we started putting the unwanted river rocks at the driveway apron.

We finished pulling all the wire last month.  We still have to cut in all the boxes so they "are ready for device" in order to schedule our rough electrical inspection.  Also have to cut in all the circuit breakers into the distribution panel.  We learned that in addition to GFCI outlets, we have to install AFCI breakers for all bedroom and smoke alarm circuits.  That was a new one for us.

There's the distribution panel, all the circuits are there.  Now just have to cut 'em in.

The garage door is finally going in.  We made the order in April of this year.  We weren't sure if it was going to snow in the garage before the door was up.  Fortunately we have avoided that.

Last panel to install..
Angel installs the track.
It is official, Eagle View residence is completely closed in and ready for winter season inside work.  Now we can lock all doors and keep our tools and materials in the house without concern of casual theft.
We spread some of the manure (frame left piles), about half of it so far.  Once all that is spread, we can start laying in the last fill layer of top soil (frame right pile) that we saved from the driveway excavation.  We want to get an irrigation header buried before we complete the final grading.  It may be spring when we get to that.
A few shots from inside.  We also took delivery of the shower unit for the master bathroom.  We plumbed the drain in and have requested a rough plumbing inspection for later this week.  Fingers crossed on the inspection results...
Some of the guest bath and laundry plumbing.
This photo below doesn't translate all that well, but what it was, was a sun dog rainbow right in front of Mt Baldy.  We have never seen such a thing so low in the sky.