Wednesday, September 30, 2020

Second Day of Framing the Shop

The remarkable thing for us on this second day with framing carpenters on the project site, was that LVE, the local electric coop also came calling to install the primary electric service conductor and the pad transformer.  Project traction is happening at Eagle View!

Below Gari observes the Bucket Crew work at the overhead lines.When we arrived onsite at 9AM the LVE crew was already working.They had already transitioned from the 2.5" electrical conduit we buried last week, to a galvanized conduit they installed that morning.  They made the transition with a piece of flexible conduit.We captured a shot of the primary conductor; insulation says it's 3 AWG aluminum.  It is a single conductor with a surrounding ground.  The overhead power lines at the street carry 3-Phase 7,200 Volts and that is sent down this primary conductor to the transformer!  The transformer will separate out two 120 volt lines that are 180 degrees out of phase to provide 240 volts across the two hot lines where needed in the Shop and home.While the Bucket Crew was waiting at the pole, the Transformer Guy is sending a string down the buried conduit to the Bucket Crew.   He did this by placing a balloon tied to the string into the conduit, now he is using his leaf blower and paying out the string as the balloon blows through the buried conduit.  That took about 2 minuets.Meanwhile, the framing crew is raising the columns they set up with joist hangers on day one.  Looks like they already have eight columns up.Look over there at the pole, there's the balloon that came through the buried conduit!The Transformer Guy ties a long and narrow towing strap to the string at the transformer and the Bucket Crew pulls the string to retrieve the stronger pulling strap at the pole.  The Bucket Crew then secured the primary conductor to the towing strap and the Transformer Guy, with a little help, will pull the conductor back through the buried conduit to the transformer.Transformer Guy preparing to start pulling the strap.  He's rigged the strap through a pulley directly over the conduit so it directs the pull force straight out of the buried conduit.Bucket Crew feeds the conductor from the spool into the conduit as Transformer Guy pulls it through.Jace from the Bucket Crew assists Transformer Guy with the last part of the pull.  You can see the conductor coming out of the conduit just now below.  It is connected to the pulling strap with a Chinese Finger Grip.Next, Transformer Guy drives an 8 ft copper ground rod with his electric jack hammer.  That is the way to do that.  It took all of 30 seconds!  Brrrrrrrrrrrrrrip!Bucket Crew extends the conduit up to the top of the pole.Meanwhile back at the transformer, Transformer Guy terminates the primary conductor .Lastly, Transformer Guy terminates the grounding and will be finished there.  The white plastic insulated terminals are the secondary hot legs 1 & 2 and are what we will send to the meter base that we will hang on the exterior Shop wall next spring.Back at the pole, Bucket Crew works the cut-in assembly with the fiberglass pole tool.  You can't be too careful around 7,200 Volts! Gari re-chinks the newly installed pad transformer with a little more 3/4 gravel.Back at the Shop job area, 2x6" wall girts begin to go in on the east wall.A little acrobatics go along with wall girt installation!You may wonder how they raise the 16 ft 6x6" columns.... the old fashioned way, with brute strength!Then hang on tight while it is steadied and lined up!Quick, get the long level on it and tack it in place!  There are 19 of these columns in this design.End of day two of framing; two walls started with girts more than half way up.  A very good day.




Friday, September 25, 2020

Biggest Day at Eagle View

Even though we have been busy most everyday with some sort of small or large planning task, or an occasional small task at the lot, most days not much happens at the lot.  Yesterday was an big exception to that trend.  Yesterday our 1500 gallon septic tank arrived and was set in the ground, we met with the local electric coop (LVE) engineer on site, and the Shop framing crew of four showed up for their first day on our job site.  To add to the excitement, we received a call from Gari's sister Sandi who was headed home to WA from a two day Antelope hunt in WY with her husband Sam.  They wanted to meet up for lunch.  Needless to say, yesterday was a big day at Eagle View!

The shot below is looking toward the southwest and shows Troy of Valley Excavation disconnecting the crane from our septic tank.  In the background you can see the Shop pad and the framing crew onsite fabricating the columns.Flashing back... Troy digs the hole for the septic tank the day before it arrived, and in the shot below he is checking the hole for proper depth.  Tomorrow the septic tank is scheduled to arrive. Below, Troy departs from his backhoe, finished for the day. Below, a little better view into the rough hole for the septic tank is seen.  Tomorrow, Troy will lay down a bed of 3/4" crushed stone as a level and smoother base for the tank.Below the finished base of the hole is seen, now we are waiting on the septic tank to arrive.

Below, another shot of the excellent base prep for the 1500 gallon septic tank.
Shazam here comes the septic tank! Troy goes out to meet the septic tank truck to give instructions to the driver Steve.
Troy directs driver Steve back to the intended septic tank hole.
Driver Steve swings the crane hoist tank over toward the resting target.
Troy uses his Pro-Only tank stick to position the septic tank just so as the crane lowers the tank into place.
Gari and Troy carefully inspect the position and condition of the tank.
Inspector #1 reviewing the safety of the back-filled tank installation.  Infiltrator chamber drain field to go in next week.
Below the framing crew is on site and underway!  First day of framing, YAHOO!Framing crew of four.Framing Crew installing sill plates and setting up wall columns.
The four corner columns below with Simpson hangers installed on adjacent sides, horizontally for the 2 ft O.C. 2x6" wall girts.
Wall columns with hangers on opposite sides for wall girts.
Shop site looking toward the Southwest.
Flash forward one day...framing crew must have come out to the site Thursday.  The sill plates were all bolted and a cargo trailer appeared on site.  Looks like the framing crew will be ready to install wall columns and wall girts next week.  We are hoping that they may even start to build up the roof truss sections.  They will connect the roof trusses with 2x6s using Simpson hangers, then they lift the roof sections onto the wall top plates with a crane.
Pressure treated sill plates all bolted down.  These plates actually become the bottom wall girt where the bottom of the wall sheathing and siding steel is fastened.  You can see the entire cargo trailer in this shot.
Inspector #1 on the framing area of the project now.
The Ufer Ground in the Shop slab for electric service.  The reinforcing steel is tied together within the concrete slab and this stub sticking out acts as a good grounding point
Gari surveys area for future a run-in shed.  Because we had to react quickly to an easement right of way request for our neighbor's electric service, we wanted to ensure that we preserved plenty of space for a future run-in shed.  We ended up preserving a 60'x30' area for the shed.  We don't believe we would build anything nearly that big, but we are not certain of the specific placement, so we left plenty of area to adjust the location when we get to that point.
We met with the Electric Coop engineer, our neighbor, his excavator (who is also a neighbor) and formulated a plan.  Then Glenn, the excavator, a recovering attorney by his own description, opened up another trench into our beautiful transformer pad.  He had a 12" bucket, so the damage and rework to the pad was not too bad.  Glenn and his sidekick Bella work below.
We reworked level on the transformer pad using a piece of discarded sill plate.  We used that wood to screed and level the 3/4" gravel, compact the gravel and by placing the smartphone on the wood while observing the bubble level app we adjusted the surface to a very plumb plane.
The beautiful reworked electric transformer pad result!
This is Gari's Highly Satisfied pose.  Hopefully she will remain in this pose next week if the Shop walls go up and the drain field is installed.